|
In This Issue: |
|
Quick Links: |
|
|
|
|
|
Recent Cases in Community Association Law
Law Reporter
provides a brief review of key court decisions throughout the U.S. each month.
These reviews give the reader an idea of the types of legal issues community
associations face and how the courts rule on them. Case reviews are
illustrations only and should not be applied to other situations. For further
information, full court rulings can usually be found online by copying the case
citation into your web browser. In addition, CAI’s College of Community
Association Lawyers prepares a case law update annually. Case law summaries along with
their references, case numbers, dates, and other data are available
online.
|
Architectural Change Must Be Considered Under Policies in Effect When Application Submitted
Adcock v. Queen's Landing Council of Unit Owners, Inc., No. 1780, Sept. Term 2019 (Md. Ct. Spec. App. Dec. 14, 2020)
Architectural Control: The Court of Special Appeals of
Maryland determined that an architectural change application had to be
considered under the policies in effect at the time the application was
submitted, not policies adopted days later.
Queen's Landing Council of Unit Owners, Inc. (association)
governed the Queen's Landing Condominiums in Chester, Md. Walter Adcock owned a
unit in the condominium.
When the condominium was constructed, the developer offered
the initial buyers the option to add dormers to their units. As a consequence,
many units had dormers, but Adcock's unit did not. In 2009, Adcock submitted an
architectural change request (first request) to the association's covenants
committee (committee), requesting permission to add dormers to his unit. The
committee denied the first request.
In 2012, Adcock resubmitted the request (second request). The
committee identified nine conditions that Adcock had to address before it would
consider the dormers. In 2015, the committee denied the second request because
Adcock still had not addressed the nine conditions. In 2016, Adcock sued the
association, claiming that the second request was improperly denied. The trial
court concluded that Adcock had failed to meet the nine conditions for dormers,
and Adcock dismissed the case.
In June 2017, Adcock submitted the dormer request again
(third request). The committee chair determined that the third request was
identical to the second request and noted that Adcock still had not satisfied
the nine conditions. In July 2017, before the committee made a final decision
on the third request, the association's board of directors (board) held a
special meeting for the purpose of amending the association's policies
regarding the limited common element roofs, which prohibited any additional
dormers from being constructed (the dormer policy). In August 2017, the
committee sent Adcock notice that the third request was denied with a copy of
the board's dormer policy attached to the notice.
The Maryland Condominium Act (act) establishes a process an
association board must follow to adopt rules, which requires prior notice to
the owners and an opportunity to comment before the rule is formally adopted. In
August 2019, the board notified the owners of its desire to formally adopt the
2017 dormer policy. After conducting the required meeting and comment period,
the board adopted the dormer policy in September 2019.
In 2018, Adcock sued the association over denial of the
third request. The trial court ruled that the dormer policy did not apply since
the third request was submitted prior to the dormer policy's formal adoption. However,
it found that the committee properly denied the third request since Adcock
still had not satisfied the nine conditions required as part of the second
request. The trial court granted summary judgment (judgment without a trial
based on undisputed facts) in the association's favor. Adcock appealed.
Adcock claimed that the committee breached its contractual
and fiduciary duties to him by failing to properly consider the third request. The
committee chair characterized the third request as "dead on arrival"
because it was identical to the second request, and Adcock still failed to
satisfy the nine conditions in the five years between the second and third
requests. However, the committee gave no reason for denying the third request;
it merely attached the dormer policy to the rejection letter. This led the
appeals court to conclude that the dormer policy was the rationale for denying
the third request.
Adcock insisted that the dormer policy was improperly
adopted by the board in 2017 since it failed to follow the act's requirements. The
appeals court agreed and found that the board's decision to formally adopt the
dormer policy again in 2019 after notice to and comment by the owners seemed to
be an acknowledgment that the 2017 adoption was invalid.
The dormer policy should not have been a factor in
considering the third request since the dormer policy had not yet been properly
adopted as required by the act. As such, the trial court should not have
granted summary judgment in the association's favor on this issue. The
committee was required to consider the third request under the bylaws and
policies as they existed at the time the third request was submitted.
Accordingly, the trial court's judgment was reversed. The
case was remanded with directions for the trial court to enter a judgment
declaring that the 2017 adoption of the dormer policy by the board violated the
act. ©2021 Community Associations Institute. All
rights reserved. Reproduction and redistribution in any form is strictly
prohibited.
[ return
to top ] |
Successor Developer Could Not Acquire Condo Development Rights After Those Rights Expired
Alibro Holdings, LLC v. The Falls at Old Henry Condominium Council, Inc., Nos. 2018-CA-1020-MR, 2018-CA-1064-MR
(Ken. Ct. App. Nov. 20, 2020)
Developmental Rights: The Court of Appeals of Kentucky held
that, once the development period stated in the condominium master deed
expires, all of the condominium property reverts to the unit owners and all
rights to construct additional units within the condominium property evaporate.
The Falls at Old Henry Condominium Council, Inc. (council)
governed The Falls condominium in Louisville, Ky.
Development of the phased condominium began in 2007. A
master deed and declaration of condominium project regime (master deed) was
recorded, establishing 12 units and common elements within the condominium
regime. The original developer submitted the entire tract of land comprising
the development (development tract) to the condominium regime, but it reserved
an expansion right for the "declarant" for five years to construct
additional units. The master deed contemplated that 37 units would be built.
Under condominium law, all of the property submitted to the
condominium regime is either a unit or common elements. The master deed
allocated a percentage of ownership interest in the common elements to each
unit and stated that such percentage interest could not be altered without the
consent of all unit owners. However, upon the declarant constructing additional
units in accordance with its reserved expansion right, the declarant could
amend the master deed to reallocate the percentage interests among the units.
The master deed gave the declarant the right to manage the
condominium and the council until the earlier of five years after the master
deed was recorded or 120 days after 95% of the contemplated units were sold to
buyers. The master deed imposed a duty on the declarant to maintain, repair,
and replace all common element improvements, specifically roadways, during the
time that it controlled the council.
The original developer built 30 units before experiencing
financial trouble. In 2011, to avoid foreclosure, the original developer signed
a deed in lieu of foreclosure conveying the development tract other than the
units to its mortgage company, Central Bank (bank). In 2012, a document was
recorded assigning the original developer's special declarant rights to the
bank. In 2013, the bank sold its interest in the development tract (minus the constructed
units) to Alibro Holdings, LLC (Alibro) for $240,000.
In 2015, Alibro constructed four units on the development
tract. Alibro recorded an amendment to the master deed identifying itself as
the successor declarant and adding the four units to the condominium regime. At
some point, the council's board of directors (board) became aware that the
declarant rights expired in December 2012, but there was no indication that the
board questioned Alibro's authority during construction.
After those four units were sold to buyers, a dispute arose
between the board and Alibro when Alibro sought to build the remaining three
units. The board wanted Alibro to top coat the roadways and make infrastructure
improvements. Alibro claimed that it was not the successor declarant and had no
responsibility for common element improvements.
In 2017, the council sued Alibro, requesting that Alibro be
declared the successor declarant and that it be required to complete the roads
and infrastructure improvements. The trial court noted that the privilege for
building the units was paid to the bank, not to the council. The trial court
concluded that Alibro could not purchase the declarant's right to build units
without also assuming the declarant's obligations. Alibro appealed.
The council insisted that Alibro held itself out as the
successor declarant in the master deed amendment submitting Alibro's units to
the condominium. The appeals court said that such characterization by Alibro
was of no importance because the amendment could not serve to revive expired
declarant rights.
The appeals court held that the bank's assignment of
property to Alibro after the five-year development period had expired was
ineffective to convey any rights to Alibro either as a declarant or a builder
because all rights in the development tract had reverted to the owners of 30
units existing at the time the rights expired. Alibro did not assume any
declarant responsibilities to complete common element improvements, but it also
had no right to build the four illegal units.
The council could have sued Alibro to stop construction, but
it did not, and it also did not contest the four units as part of this lawsuit.
Therefore, the appeals court did not address any potential claims the council
may have against Alibro with respect to the four units. The appeals court
stated that, if Alibro wants to build the last three units, it must negotiate
with the council to acquire such rights. The council could amend the master
deed to permit further development.
Accordingly, the trial court's judgment holding that Alibro
had no responsibilities as the declarant was affirmed, but the portion of the
trial court's judgment stating that Alibro must assume declarant
responsibilities if it constructs units was reversed. ©2021 Community Associations Institute. All
rights reserved. Reproduction and redistribution in any form is strictly
prohibited.
[ return
to top ] |
Successor Developer Liable for All Common Area Construction Defects
Brooktree Village Homeowners Association, Inc. v. Brooktree
Village, LLC, No. 19CA1635 (Colo. Ct. App. Nov. 19, 2020)
Developer Liability; Construction Defects: The Court of
Appeals of Colorado held that, under the Colorado Common Interest Ownership Act,
an association could recover the entire cost of repairing common area
construction defects from a successor developer.
Brooktree Village Homeowners Association, Inc. (association)
governed the Brooktree Village Townhomes development in El Paso County, Colo. The
original developer constructed two of the planned 14 buildings, completing
seven townhomes in total, and finished half of the roadways. It also completed
the grading for the entire development site.
However, the original developer experienced financial
difficulties and filed for bankruptcy. The original developer's lender foreclosed
on the remainder of the development. The lender conveyed the development's common
areas to the association.
Brooktree Village, LLC (successor developer) bought the
remaining undeveloped property from the lender. Through its affiliated
construction company, Rivers Development, Inc. (builder), the successor
developer completed construction of the remaining 12 buildings (including 45
townhomes), common areas, and roadways contemplated by the project's
declaration of covenants, conditions, restrictions, and easements (declaration)
in accordance with the original plans. By 2015, the successor developer had
completed and sold all of the townhomes.
As early as 2012, owners began reporting construction
defects to the builder. When the association was unable to reach a resolution
with the successor developer and the builder (collectively, the defendants),
the association filed suit in May 2017. The alleged problems primarily related
to improper site grading and drainage, causing water accumulation and intrusion
into the homes, concrete cracking and settling, and movement of concrete
basement slabs.
The association asserted claims on behalf of itself and all
owners under the Colorado Common Interest Ownership Act (CCIOA) for breach of
implied warranty and negligence. Colorado law reads an implied warranty of
workmanlike construction and fitness for habitability into all agreements for
the sale of new construction between builder-sellers and purchasers. A jury
found that the defendants were liable for breach of implied warranty and
negligence and awarded the association more than $1.8 million in damages. The
defendants appealed.
The defendants argued that the association had no claim
against them for the common area defects because the defendants never owned the
common areas or transferred them to the association. Also, the owners had no
relationship to the builder, and most of the owners at the time of the lawsuit
had no relationship to the successor developer since many were resale
purchasers who bought from other owners.
Only persons in a contractual relationship with a builder or
seller (referred to as privity of contract) have implied warranties, so an
implied warranty is limited to the first purchaser of the home. The purpose of
the privity requirement is to protect sellers from claims by buyers who are not
within the class of those reasonably intended to be protected when the home was
offered for sale. Although the builder did not sell the homes directly to
purchasers, it knew the initial homeowner was the intended purchaser. The builder
created the successor developer to market and sell the townhomes that the builder
constructed, so the appeals court considered it to be illogical to not impose
an implied warranty on the builder.
The appeals court agreed that the defendants were not in
privity with the association. They were also not in privity with the owners who
did not purchase homes from them. As such, neither the association nor the
resale purchasers received implied warranties from the defendants based on any
contractual right.
However, all of the owners had easement rights in the common
areas based on their deeds and the declaration. Consequently, a construction
defect located anywhere in the project affected the rights of every owner. Under
the CCIOA, an association has a right to intervene in litigation on behalf of
two or more owners on matters affecting the community. This allows an association
to pursue claims for breach of implied warranty to fix construction defects in
individual units, in addition to defects in the common areas, because
individual units are a part of the community.
The defendants argued that they could only be held
responsible for a percentage of the total damages for common area defects based
on the number of homes they sold to current owners relative to the entire
development. The appeals court thought it unreasonable to discount the damages
because it would mean that the association could recover only about 44% of the total
common area damage costs. It would not give the defendants' purchasers an
adequate remedy to repair only half of the common areas.
The appeals court held that, under the CCIOA, an association
may recover the entire cost of repairing common area construction defects from
a successor developer or builder if the defects were attributable to the
successor developer or builder, two or more owners purchased homes directly
from the successor developer or builder, and those owners had rights to use the
common areas.
The defendants argued that the association could not assert
claims for common area defects affecting individual homes unless the owners of
those homes assigned their claims to the association, but the appeals court
held that the association had standing to assert such claims without the
necessity of an assignment from the owners.
Accordingly, the trial court's judgment was affirmed. ©2021 Community Associations Institute. All
rights reserved. Reproduction and redistribution in any form is strictly
prohibited.
[ return
to top ] |
Board Violates Condominium Documents by Changing Assessment Allocation Methodology
Gerfman Global, LLC v. Kershaw, 99 Mass. App. Ct.
1103 (Mass. App. Ct. Dec. 14, 2020)
Assessments: The Appeals Court of Massachusetts held that a condominium
board violated the condominium documents by not properly allocating expenses to
residential and commercial units to separate budgets.
Nautica Leasehold Condominium Trust (trust) governed the
Nautica condominium in Charlestown, Mass. The condominium consisted of eight
buildings containing 117 residential units and an underground parking garage
comprising two commercial parking garage units (garage units). Gerfman Global,
LLC (Gerfman) owned the two garage units.
The common elements consisted of all the property in the
condominium outside of the individual units. The condominium master deed
(master deed) described condominium common elements (CCE), which were for the
use and benefit of all units, as well as residential common elements (RCE),
which served only the residential units. The master deed assigned a percentage
interest in the common elements to each unit. The garage units were assigned a combined
17.967% interest in the CCE, and the residential units were assigned the
remaining 82.033% interest in the CCE. The residential units were assigned 100%
of the interest in the RCE. There were no separate common elements that related
just to the garage units.
The master deed provided that the cost of maintaining and
operating the CCE and the RCE were to be allocated among the units in
accordance with the percentage interests. This meant that the garage units were
responsible for 17.967% of the CCE costs and none of the RCE costs. The
residential units were responsible for 100% of the RCE costs plus 82.033% of
the CCE costs.
Since at least 2001, the trust's management company
allocated only the cost of the condominium master insurance to the CCE budget. All
other trust expenses were included in the RCE budget. However, beginning in
2013, the management company changed its practice based on direction from the
board of trustees (board). The board took the position that any expense related
in any way to the garage units would be allocated entirely to the CCE budget.
Gerfman objected to the new allocation method and stopped
paying its assessments in January 2013. Matthew Hoffman was a member of Gerfman
and also on the board. In October 2013, Gerfman sued the four members of the
board besides Hoffman. Gerfman sought a declaration that the master deed
required the board to account separately for income and expenses associated
with the distinct CCE and RCE budget categories. Gerfman contended that the
board's change in the budget methodology impermissibly shifted RCE expenses
onto the owner of the garage units.
The trial court found that the new budget methodology
clearly shifted expenses and costs related to residential units onto the garage
units. For example, if a maintenance person spent most of their time on
resident requests and servicing the residential buildings and a small fraction
of time overseeing CCE, then 100% of such person's cost was allocated to the
CCE budget. The trial court found that such practice was not in compliance with
the master deed or industry standard. The trust also did not maintain separate
reserve accounts for CCE and RCE. The budget combined the RCE and CCE expenses
and assessed a 10% contribution to a general reserve account to the residential
unit owners.
The trial court determined that "indivisible"
expenses should be allocated to the CCE budget, but expenses incurred
specifically for RCE areas should be allocated to RCE. The trial court found
that common expenses such as legal fees, office expenses, management costs, and
fees for professional consultants could be divided and budgeted separately
between CCE and RCE.
The trial court held that the master deed required the board
to distinguish between CCE and RCE within each budget line item and that the
board was required to establish separate reserve accounts for CCE and RCE. It
declared that the assessments charged to Gerfman under the new methodology were
invalid, and assessments made subsequent to May 2016 were unenforceable. Both
parties appealed.
The board argued that the trial court's ruling would lead to
the inequitable result of forcing the residential unit owners to bear virtually
all of the common element expenses, even though the garage units received a
substantial benefit from the common elements. The board asserted that such a
methodology would force the residential unit owners to subsidize the owner of
the garage units.
The appeals court found no error in the trial court's
judgment. The trial court was clear that there was a category of indivisible
expenses that could be allocated entirely to CCE and did not have to be divided
between the two categories. However, the board was not permitted to simply lump
all expenses in the CCE category.
Gerfman argued that it should be able to recover assessment
overpayments beginning in January 2013, not May 2016. In order for a party to
recover for overpayment, the party must pay the assessment when due, while
preserving the right to contest the charge by making the payment "under
protest." Gerfman failed to pay the monthly assessments for January
through April 2013, at which point Hoffman made Gerfman's objection known to
the board. Gerfman did eventually pay the assessments requested, but it was
months and years after the amounts were due.
Accordingly, the trial court's judgment was affirmed. ©2021 Community Associations Institute. All
rights reserved. Reproduction and redistribution in any form is strictly
prohibited.
[ return
to top ] |
Developer Could Not Make Lot Subject to Declaration Years After Lot Sold
Kadar-Kallen v. Old Iron Estates Homeowners Association, No. 1671 C.D. 2019 (Pa. Commw. Ct. Dec. 3, 2020)
Documents: The Commonwealth Court of Pennsylvania held that a lot was
not subject to the declaration because the developer did not own the lot at the
time the declaration was recorded, but the lot owner could still be obligated
to contribute to common area maintenance if the owner benefitted from the
common area.
Old Iron Estates Homeowners Association (association)
governed the Old Iron Estates subdivision in Dauphin County, Pa. Michael and
Kimberlee Kadar-Kallen (the Kadar-Kallens) owned lot 41 in the community.
The community was developed in four phases. The phase 1 plan
referred to a total tract area of 91 acres, but it detailed only 29 acres as
the phase 1 area and stated that 31 lots were proposed. In 2003, the developer
recorded restrictions, covenants, and conditions (declaration), which stated
that the declaration would be binding on the property described in the recorded
phase 1 plan.
In 2005, the developer sold lot 41 to John Fox. Lot 41 was
not part of the phase 1 area, but it was included in the larger 91-acre total
tract area. In 2007, Fox sold lot 41 to the Kadar-Kallens. The Kadar-Kallens
paid an initiation fee to the association at the time of their purchase. Their
purchase agreement disclosed that the property was part of a planned community,
their mortgage included a planned unit development rider, and their title
insurance policy referenced the association.
The developer later recorded plans for phases 2, 3, and 4 as
well as a separate declaration for each phase that was identical to the phase 1
declaration. The phase 3 declaration recorded in 2012 contained a list of
parcels to which it applied, which included lot 41. However, the Kadar-Kallens
owned the lot at the time, and they did not sign the phase 3 declaration.
In 2017, the Kadar-Kallens sued the association, seeking a
determination that they were not association members and were not subject to
the declaration. The trial court granted summary judgment (judgment without a
trial based on undisputed facts) in the Kadar-Kallens' favor. The association
appealed.
The association insisted that the phase 1 declaration
established a planned unit development and was sufficient to bind the entire
91-acre tract. It argued that the recording of the phase 3 declaration was done
out of an abundance of caution and was not necessary to make future phases
subject to the declaration. The association contended that the Kadar-Kallens
had both actual and constructive knowledge of the association when they
purchased lot 41 based on the representations in their purchase contract and
mortgage documents.
The appeals court found that the phase 1 declaration
unambiguously referred only to the phase 1 lots. Although the phase 1 plan
contained a single reference to the broader 91-acre tract, only the 29 acres in
phase 1 were described or detailed. Importantly, the developer did not reserve
any rights to expand the subdivision. Rather, separate plans and separate
declarations were filed for additional phases. The appeals court viewed the
additional phase declarations as evidence that the developer knew the lots in
those phases were not bound by the original declaration.
The phase 1 declaration was clearly insufficient to bind lot
41. While lot 41 was mentioned in the phase 3 declaration, the developer had no
authority to subject lot 41 to the phase 3 declaration since it no longer owned
the lot at the time the phase 3 declaration was signed and recorded. Neither
the deed for lot 41 from the developer to Fox or the deed from Fox to the
Kadar-Kallens mentioned anything about a homeowners association or the right to
use any common area in Old Iron Estates.
However, the fact that lot 41 was not subject to a
declaration was not the end of the analysis. An additional consideration is
whether an owner derives any benefit from an association or its common
facilities so as to trigger an obligation to contribute to the association's
costs of maintaining the common facilities. The parties had not submitted
evidence showing whether the association was responsible for maintaining the
community's roads, which the Kadar-Kallens depended on for access to their lot.
Accordingly, the appeals court affirmed the trial court's
judgment that lot 41 was not bound by the phase 1 declaration or the phase 3
declaration. However, the appeals court vacated that portion of the judgment,
concluding that the Kadar-Kallens were not obligated to contribute to the costs
of maintaining common facilities, and the case was remanded for further
development of such issue. ©2021 Community Associations Institute. All
rights reserved. Reproduction and redistribution in any form is strictly
prohibited.
[ return
to top ] |
Short-Term Rentals Are Not a Business Use
Lastavich v. Nob Hill Homeowners Association, No. D075466 (Cal. Ct. App. Dec. 2, 2020)
Use Restrictions: The Court of Appeal of California held that, absent an
express prohibition in a declaration, short-term rentals did not constitute a
business use in violation of a residential use restriction.
Nob Hill Homeowners Association (association) governed a
four-unit condominium in Carlsbad, Calif. Louis Lastavich, Bill Cima, and Spiro
Demis owned units in the condominium.
In 2017, Lastavich sued the association, Cima, and Demis
(collectively, the defendants), seeking, among other things, to bar the
defendants from using the condominium for short-term vacation rentals. Lastavich
asserted that short-term rentals violated the Nob Hill declaration of
covenants, conditions, and restrictions (declaration), which require each unit
to be used as a single-family residence and for no other purpose.
Lastavich purchased his unit in 1995 and had continuously
resided in it. Cima purchased his unit in 1998. The unit was used for long-term
rentals until 2005 and for short-term rentals thereafter. Demis had used his
unit continuously for short-term rentals since his purchase in 2008.
The trial court determined that using a unit for short-term
rentals did not constitute the operation of a business in violation of the
residential use restriction. Lastavich appealed.
The appeals court found that the evidence clearly
established that the use of the units as vacation rentals was neither
unexpected nor unanticipated. The condominium was located in the coastal zone
of a beach resort town. Most of the current and former owners dating back to
2005 had used their units for short-term vacation rentals. The original
developer also testified that she had no intention of creating a minimum lease
term in the declaration.
The declaration contained no express minimum lease term. Several
provisions of the declaration distinguished between owners, tenants, and
guests, but there was no language defining a tenant as only occupying a unit
for more than 30 days.
Restrictions on the use of land will not be inferred or read
into a declaration without an expression in the declaration of an intention to
limit the land's use. Absent any express, unambiguous prohibition on short-term
leasing in the declaration, the declaration's terms must be strictly
interpreted in favor of the free use of the property. Moreover, the Nob Hill
units had historically been used for vacation rentals.
Accordingly, the trial court's judgment was affirmed. ©2021 Community Associations Institute. All
rights reserved. Reproduction and redistribution in any form is strictly
prohibited.
[ return
to top ] |
Homeowners Cannot Enforce Stormwater Facility Maintenance Obligations of Adjacent Shopping Center
Mallavarapu v. City of Cedar Falls, No.
19-1792 (Iowa Ct. App. Dec. 16, 2020)
Contracts: The Court of Appeals of Iowa held that owners of residential
property adjacent to a stormwater detention facility built by a shopping center
developer had no rights to enforce the maintenance obligations of an agreement
between the city and the developer concerning the facility, even though the
facility was partly for scenic and recreational purposes.
In 1997, Thunder Ridge L.P. (commercial developer) entered
into a stormwater easement agreement (easement agreement) with the City of
Cedar Falls, Iowa (city), relating to development of a five-lot shopping
center. The easement agreement granted a perpetual easement to the commercial
developer to construct and maintain a stormwater detention and drainage
facility for the benefit of the owners of the five commercial lots.
If the commercial developer did not maintain the detention
facility as required by the city's standards, the city had the right to enforce
the easement agreement's maintenance obligations. Thunder Ridge West Owners
Association (commercial association) was formed to represent to the commercial
owners, and the commercial developer's responsibility under the easement
agreement was transferred to the commercial association.
In 1999, Ridges Development L.P. (residential developer)
conveyed two tracts of land to the commercial developer for the primary purpose
of use as a stormwater and surface drainage and detention facility. In the
transfer, the residential developer reserves for itself a secondary easement
over the property for recreation and beautification purposes. In a recreation
easement agreement (recreation agreement), the commercial developer and the
residential developer agreed to share the property for both recreational and
stormwater detention purposes, but the recreation agreement stated that the
dominant purpose of the property was for a stormwater detention and drainage
facility.
The city hired an engineer to design a wet detention basin
that could serve as a drainage facility with a permanent pond feature for
recreational and aesthetic purposes. The residential developer developed the
Ridges Park neighborhood bordering the detention basin. For some of the home
purchasers, the water feature was a major factor influencing their purchase
decision. The homeowners used the pond for fishing, paddle boating, and taking
scenic strolls around the shore.
However, over time, the pond's water quality diminished. There
was significant algae and vegetation growth, and the water smelled. The water
level also diminished substantially, making the pond less visually appealing. Ravindra
Mallavarapu and six other homeowners (the concerned owners) asked Ridges Park
Homeowners Association (residential association), the association governing
Ridges Park, for help in improving the water quality in the detention basin
abutting their backyards.
The residential association hired an engineering firm to
investigate the detention basin. The investigation revealed that the pond's
water level was about 40% of its original design volume, and accumulated silt
was the main culprit. The engineer said the pond's shallow depth made it unfit
for recreation, and the pond would become a nuisance as silt continued to build
up. The engineer recommended that the pond be drained, the accumulated sediment
removed, and the pond bottom and sides restored to the original design.
The concerned owners demanded that the city take action to
enforce the maintenance requirements of the easement agreement based on the
significant health risk and recreation use concerns. When the city took no
action, the concerned owners sued the city and the commercial association,
seeking to enforce the easement agreement's maintenance requirements.
The trial court recognized that the concerned owners were
not parties to either the easement agreement or the recreation agreement, but
it decided they were entitled to relief as incidental beneficiaries because
they obviously obtained a benefit from the easements. However, the trial court
determined that the city engineer had the exclusive authority to determine when
maintenance was required, and he had determined that no additional maintenance
of the detention basin was required. Both sides appealed.
The appeals court said that there was a distinction between
incidental beneficiaries and intended beneficiaries. In order for a person who
is not a party to a contract to have standing to assert a claim for breach of
the contract, the person must be regarded as an intended beneficiary of the
contract, not merely an incidental beneficiary. No duty is owed to a person who
is not party to a contract unless the third party is intended to be a
beneficiary of the contract. The main consideration is whether the contract
expresses an intent to benefit a third party.
The appeals court found nothing in the easement agreement
that expressed an intent that owners of homes abutting the detention basin
obtained the legal right to enforce the maintenance provisions. Instead, the
easement agreement was for the benefit of the general public that could be
affected by runoff from the shopping center, not for any specific landowners. The
city was concerned about localized flooding caused by uncontrolled stormwater
runoff.
The easement agreement did not suggest that the commercial
developer would maintain the water quality in the detention basin in line with
the expectations of neighboring homeowners. Nothing in the easement agreement
suggested that the city intended to directly or primarily protect homeowners in
Ridges Park when it contracted with the commercial developer to construct and
maintain the detention basin.
The concerned owners claimed they were in immediate danger
due to the algae in the pond, which also caused their home values to diminish. However,
the appeals court found that harms of that nature were outside the scope of
what was contemplated by the easement agreement. The appeals court held that
the concerned owners did not have standing to enforce the easement agreement.
Accordingly, the trial court's judgment was affirmed. ©2021 Community Associations Institute. All
rights reserved. Reproduction and redistribution in any form is strictly
prohibited.
[ return
to top ] |
Architectural Control Committee Does Not Have a Fiduciary Duty to Owner
Pittenger v. Gleneagles Homes Association,
No. 18 CVS 11280 (N.C. Super. Ct. Dec. 1, 2020)
Architectural Control: The North Carolina Superior Court of
Mecklenburg County held that an association architectural control committee did
not owe owners a fiduciary duty when reviewing architectural applications; the
committee owed only the association a duty to act reasonably and in good faith
in evaluating applications under the declaration's requirements.
Gleneagles Homes Association (association) governed the
Quail Hollow subdivision in Charlotte, N.C. Robert and Suzanne Pittenger (the
Pittengers) owned a home in the community. Doug Lebda and Megan Greuling (the
Lebda-Greulings) owned the lot next door.
In accordance with the community's declaration of covenants,
conditions, and restrictions (declaration), the Lebda-Greulings submitted plans
to the association's architectural review committee (ARC) for approval to
construct a home on their property. The declaration prohibited the construction
of any structure other than a dwelling not to exceed 2 1/2 stories in height
above ground level, a private garage or carport for no more than four cars, and
other outbuildings incidental to residential use.
The Lebda-Greuling plans depicted a five-car garage. Five-car
garages had previously been approved in the community, and the ARC believed the
number of garage bays fit with the scale of the house and seemed appropriate
based on what could be seen from the street. The ARC voted to waive the
four-car garage requirement in light of the evolving nature of the community.
The declaration did not define "story" or
"above ground level," but the ARC had always considered the height
limitation to be based on what could be viewed from the street in front of the
home. As such, the ARC considered the plans to satisfy the height limitation. It
also determined that the home was similar in structure to other homes in the
neighborhood with walkout basements. The ARC approved the plans.
After construction began, the Pittengers notified the
Lebda-Greulings that the home violated the declaration with respect to the
height, the number of garage bays, and a 10-foot building setback from the
boundary line between the two lots. The ARC considered the Pittengers'
complaints but stood by its original decision. As construction proceeded, the
Lebda-Greulings learned that a cantilevered bay or "bump-out" on the
home was over the 10-foot setback line due to a surveying error. The ARC said
it would not grant a waiver for the bump-out, and Lebda agreed to remove it.
The Pittengers raised concerns that the windows on the
Lebda-Greuling home facing their property would allow people to see the
Pittengers' backyard and eliminate any privacy they previously enjoyed. Lebda
agreed to replace the planned full-size windows on that side of the home with
transom windows that would be smaller and located higher on the walls, which
would still allow light in but prevent a direct view into the Pittengers' yard.
During an on-site inspection, the ARC discovered another
violation of the 10-foot setback. Since the building foundation was set closer
to the setback line than planned due to the surveying error, the installation
of the proposed 4-inch-thick limestone veneer to the foundation would cross the
setback line by about 2 to 2.5 inches. After considering that Lebda had already
agreed to remove the bump-out, the ARC voted to waive this minor violation.
The Pittengers sued the association, the ARC members, and
the Lebda-Greulings, contending that the home violated the declaration and that
the multiple violations amounted to a nuisance. They also asserted that the ARC
members violated fiduciary duties owed to them.
The court determined that it must defer to the ARC's
decision when it was made reasonably and in good faith since the declaration
vested authority in the ARC to approve design and landscape plans for the
community. To overcome such deference, the Pittengers had to show that the ARC
acted arbitrarily and capriciously. The Pittengers argued that the ARC members
owed them a fiduciary duty based on the "total domination and
control" that the ARC had over the property owners' rights with respect to
design and construction matters. However, the court found no basis for imposing
on the ARC members a fiduciary duty to individual homeowners beyond the duty
owed to the association to implement the declaration's requirements reasonably
and in good faith.
The court determined that the ARC was vested with reasonable
discretion to conform its enforcement of the declaration to the changing nature
of the overall subdivision as it matured and evolved over the more than 45
years since the declaration was first recorded. The court found that the ARC
members reasonably considered the prior approvals of other five-car garages as
well as the home's view from the street when deciding to waive the garage size
restriction.
In addition, although experts offered differing opinions as
to how the number of stories should be calculated, the declaration did not
specify how the height restriction should be applied. The ARC was fully aware
of the height restriction and evaluated the home's height based on historical
practices applied to other homes in the community.
The ARC acknowledged that the foundation veneer crossed the
setback line by a couple of inches due to an unintentional surveying error. However,
the declaration gave the ARC the express authority to waive any violation of
the setback restrictions that did not exceed 10% of the applicable restriction
where the violation was unintentional. The Pittengers offered no evidence that
the ARC members acted arbitrarily, capriciously, or in bad faith when deciding
that the home did not violate the height restriction and granting waivers for
the garage size and minor setback violations.
Accordingly, the Pittengers' claims were dismissed with
prejudice.
©2021 Community Associations Institute. All rights
reserved. Reproduction and redistribution in any form is strictly prohibited.
[ return
to top ] |
|